Thursday, December 10, 2009

Exterior Systems 90% complete

The process of installing exterior panels is 90% complete. The final sections, which will be completed in the coming weeks, include the Alucobond paneling located at the loading dock and a section of panels at the northern most part of the building.

Crews have finished installing the cedar accents on the exterior of the building. They are now installing cedar in the main lobby pavilion. These accents will be found in the area adjacent to the main stairs and on the terrace, adjacent to the pavilion.

Facts about the cedar being installed at the Carpenters Center (as previously posted)

  • The western red cedar has a custom tongue and groove shape, giving it a unique appearance and stronger interlocking connection than typical tongue and groove products.
  • The cedar is from 100 year old trees and has roughly 15 rings per inch, making it a long-lasting product with an expected lifetime of 50 years.
  • The cedar sealant is a water-soluble silicone based water-proofer that is less harsh on the environment than oil based products and emits no VOCs (Volatile Organic Compounds).

No comments: